Kick out flashing for stucco 2019 detail.
Flashing flat roof to stucco wall.
Flash onto the surface of the existing stucco.
Flashing a nail flange window 2018 rev detail.
Slide a 6x6 galvanized flashing up behind the stucco and paper.
When the plywood deck is in place slide the 6x6 flashing down to the deck and nail to the deck at the outside edge of the flashing.
Wall to roof deck flashing 2020 detail.
Alternatively if allowed install painted metal wall panels from roof flashing up and under existing cap flashing.
Sill pan for nail flange windows 2020 detail.
Bigger step flashing is better.
The narrower step flashing just isn t wide enough to protect the intersection fully.
The new roof is sealed to the flashing you just installed.
I recommend 12 in wide step flashings bent for a 5 in.
The metal flashing is formed with a hook edge and cleated on 12 centers.
Weep screed for stucco 2020 detail.
It cannot be pulled out from behind the stucco because the weep screen at the bottom of the stucco is attached to the wall with nails.
If you do all this carefully and neatly the existing stucco stays and looks fine.
Typically made of aluminium or galvanized steel flashing is any material used over joints in your walls or roof to prevent water from seeping through.
The flashing extends onto the roof a minimum of 2 inches 4 inches is preferable in more severe climate areas.
Applying flashing to a stucco roof or walls requires both cement and nails as well as caulk or more stucco to create a water tight seal.
The new step flashing must extend up the wall a minimum of 4 and must be laced with each course of the new asphalt shingles.
Slip the wall leg of the weep screed behind the existing paper.
Control joint at floor line 2016 detail.
Finally the housewrap can be laid up on the wall to cover the top of the kickout diverter and step flashings.
Lay 2x4 blocks on the roof to set a consistent height for the weep screed flashing.
The new roof is going to be laminated asphalt shingles.
Roof leg and a 7 in.
Cantilevered deck joist stucco 2020 detail.
Wrap the top of the wall with the wrb and install a new cap flashing.
In this video kirk giordano demonstrates how to counter flash the bottom of a stucco wall over the step flashing of the roof so that no one has to jackhammer your walls just to fix a roof.